the proposed development will comprise a 208MW (electrical output) Open Cycle Gas Turbine (OCGT) Power Plant & comprises the following elements: a) 4 No containerised Peaker Plant units (each 248m2 and c. 8m wide x 31m long x 3.5m high), each housing a fully enclosed & roofed turbo generator comprising of 2No. turbines with a common generator, all on a concrete plinth of 615m2; b) Each unit has two exhaust stacks (15m in height) one for each turbine; c) Water treatment plant comprising: 275m2 Water Treatment (Demineralisation) Building (6m high x 11m wide x 25m long); a 120m2 raw water treatment tank of 1000m3 (c. 10m high); a 315m2 deionized (treated water) water storage tank (max. volume of 4900m3) c. 16m high; hydrochloric acid tank (5m3) c. 3m high; sodium hydroxide tank (2.5m3) c.2m high; waste water storage tank (40m3) (c.2.5m high); 25m2 Firewater Module measuring 5m wide x 5m length x 5m high; Foul water pump station (slab area of 121m2) d) 2 No Fuel storage tanks to each hold a maximum volume of 4,900m3 per tank (each c. 16m high), & associated fuel pumping & filtering equipment & pipework, all within a 2350m2 concrete bund e) 3 No. Waste Storage Containers, each 80m2 (c. 3m wide x 26m length x 4m high) f) Diesel Generator with floor area of 32m2 (c. 4m wide x 8m length x 4m high) g) 2 No transformers each 160m2, & each measuring c. 8m wide x 10m length x 9m high h) a 830m2 Office & ancillary services building (c. 20 wide x 47 length x 6m high) i) a 570m2 Switchgear (MV) building (c. 13 wide x 54 length x 5m high) j) all other miscellaneous & ancillary site works, including:12 No. Car parking spaces & 3No unloading bays, widened & upgraded entrance from the R152, two lowered site platform areas & internal circulation road & hard & soft landscaping, a temorary construction compound, & palisade fencing. k) New road markings, including deceleration lane approaching the site, on the R152. The proposed development will include connection to public water & wastewater provision, supplied by Irish Water. The application relates to a development which comprises or is for the purposes of an activity requiring an Industrial Emissions Directive (IED) licence & full details of the proposed development & its anticipated environmental impacts will be notified to the Environmental Protection Agency. A Natura Impact Statement (NIS) accompanies this application
a 208MW (electrical output) Open Cycle Gas Turbine (OCGT) Power Plant & comprises the following elements: a) 4 No containerised Peaker Plant units (each 248m2 and c. 8m wide x 31m long x 3.5m high), each housing a fully enclosed & roofed turbo generator comprising of 2No. turbines with a common generator, all on a concrete plinth of 615m2; b) Each unit has two exhaust stacks (15m in height) one for each turbine; c) Water treatment plant comprising: 275m2 Water Treatment (Demineralisation) Building (6m high x 11m wide x 25m long); a 120m2 raw water treatment tank of 1000m3 (c. 10m high); a 315m2 deionized (treated water) water storage tank (max. volume of 4900m3) c. 16m high; hydrochloric acid tank (5m3) c. 3m high; sodium hydroxide tank (2.5m3) c.2m high; waste water storage tank (40m3) (c.2.5m high); 25m2 Firewater Module measuring 5m wide x 5m length x 5m high; Foul water pump station (slab area of 121m2) d) 2 No Fuel storage tanks to each hold a maximum volume of 4,900m3 per tank (each c. 16m high), & associated fuel pumping & filtering equipment & pipework, all within a 2350m2 concrete bund e) 3 No. Waste Storage Containers, each 80m2 (c. 3m wide x 26m length x 4m high) f) Diesel Generator with floor area of 32m2 (c. 4m wide x 8m length x 4m high) g) 2 No transformers each 160m2, & each measuring c. 8m wide x 10m length x 9m high h) a 830m2 Office & ancillary services building (c. 20 wide x 47 length x 6m high) i) a 570m2 Switchgear (MV) building (c. 13 wide x 54 length x 5m high) j) all other miscellaneous & ancillary site works, including:12 No. Car parking spaces & 3No unloading bays, widened & upgraded entrance from the R152, two lowered site platform areas & internal circulation road & hard & soft landscaping, a temporary construction compound, & palisade fencing. k) New road markings, including deceleration lane approaching the site, on the R152. The proposed development will include connection to public water & wastewater provision, supplied by Irish Water. The application relates to a development which comprises or is for the purposes of an activity requiring an Industrial Emissions Directive (IED) licence & full details of the proposed development & its anticipated environmental impacts will be notified to the Environmental Protection Agency.The proposed development is planned to connect to a new 110kV substation to be located adjacent and to the south-west of the proposed OCGT Power Plant. A NIS accompanies the application. Significant
alterations to a previously approved development consisting of 400MW electricity generating plant and associated structures, plant and equipment. The alterations that are the subject of this application involve the replacement of the approved water cooling system with an air cooled condenser (approx dimensions 70m x 70m x 34.5m high), increate in size of the approved surface water attenuation pond (by approx 530m2) and the relocation of some associated equipment and structures including the approved pump house. The cooling system is an ancillary use to the permitted power plant. This application relates to an activity, for which a licence under part IV of the Environment Protection Act 1992 applies and to an establishment to which the European Communities (Control of Major Accident Hazards involving dangerous substances) Regulations, 2000 (SI 476 of 2000) applies.
will consist of 60MW open cycle gas turbine power generation plant. The development comprises of the following elements: (a) a 663sq.m gas turbine building (approx. 17m wide x 41m length x 7m high) housing a fully enclosed and roofed turbo generator annexed with a similarly enclosed maintenance bay (b) associated exhaust gas stack (approx. 20m high x 2.8m diameter) and other associated stacks and vents (not exceeding 13m in height) (c) an associated air filter (approx. 15.5m high x 6.8m wide x 7.67 length) (d) a compound adjacent to the gas turbine building containing a main and an auxiliary transformer and a firewater module (e) a 316sq.m office and ancillary services building (approx. 11m wide x 31m length x 5m high) (f) 2 no. 750 cubic metre volume fuel oil tanks with concrete bund ( approx. 7.5m high) (g) 2 no. 560 cubic metre volume raw and treated water storage tanks (approx. 7.5m high) (h) a new foul sewer pipe connecting to the duleek sewer system and a new water supply pipe (i) 6 no. car parking spaces and misc. site works including an upgraded and relocated access from the R152 and internal circulation road and hard soft landscaping. Note: all heights are above existing ground levels. The application relates to a development which comprises or is for the purposes of an activity requiring an Integrated Pollution Prevention and Control Licence
No Environment Impact Assesments Associated with this Application