File No |
Staus |
Type |
Decision |
Received Date |
Name |
Development Address |
Description |
21791 |
APPLICATION FINALISED |
EXTENTION OF DURATION |
C |
27/04/2021 Tuesday |
DP Pizza Ltd, |
City North Business Campus Gormanstown Stamullen, Co Meath |
EXTENSION OF DURATION OF PLANNING APPLICATION AA/160168 - the development will consist of construction of a Warehouse/Food Processing building with ancillary two storey office and staff facilities comprising a total gross floor area of 3,645 sq.m, vehicle access from existing access, new HGV access & yard, parking for 57 no. cars & 11 no. HGV's, ESB Sub-Station and all associated site and development works and landscaping |
AA160168 |
APPLICATION FINALISED |
PERMISSION |
C |
26/02/2016 Friday |
McGarrell Reilly Management Ltd. |
Unit 6, City North Business Campus Gormanston, Stamullen Co. Meath |
the development will consist of construction of a Warehouse/Food Processing building with ancillary two storey office and staff facilities comprising a total gross floor area of 3,645 sq.m, vehicle access from existing access, new HGV access & yard, parking for 57 no. cars & 11 no. HGV's, ESB Sub-Station and all associated site and development works and landscaping |
sa40505 |
APPLICATION FINALISED |
PERMISSION |
C |
21/12/2004 Tuesday |
McGarrell Reilly Contractors Ltd |
Gormanston Co. Meath
|
the construction of a part 1 storey, part 4 storey plus penthouse hotel, comprising of 136 no. bedrooms and 1 no. 2 bed hotel suite(6312 sq.m gross in total). The hotel will comprise foyer, reception , business centre and meeting rooms, bar, restaurant and ancillary facilities and 30 no. hotel bedrooms at ground floor, 36 no. bedrooms at first floor, 36 no. bedrooms at second floor, 34 no. bedrooms at third floor and 1 no. 2 bedroom hotel suite over third floor and penthouse level. Also, 206 no. car parking spaces, 2 no. bus parking spaces and external service area associated with hotel; hard and soft landscaping; set down area external to hotel; and associated development and infrastructural services works. A new accesss road will be constructed from the existing M1 interchange(on part land owned by Meath County Council) to the south of the proposed hotel. A new roundabout will be constructed at the south west corner of the site at the end of this new road. Access to the proposed hotel will be via new access roads to the west and north site boundaries from the new roundabout |
sa60007 |
APPLICATION FINALISED |
PERMISSION |
C |
09/01/2006 Monday |
McGarrell Reilly |
Gormanstown Co. Meath
|
modifications to a previously permitted hotel development under Meath County Council Register Reference SA/40505 modifications to amendment of planning application boundary to facilitate re-alignment of the permitted access road from the existing M1 interchange to the south of the permitted hotel, re-positioning of the permitted roundabout at the south west corner of the site, and consequential amendments to the car parking layout and landscaping to the hotel forefront. |
sa60011 |
APPLICATION FINALISED |
PERMISSION |
C |
23/01/2006 Monday |
McGarrell Reilly Contractors |
Gormanston Co Meath
|
modifications to a previously permitted hotel development under Meath County Council Register Ref no. SA40505 . This permitted development is subject to concurrent planning application reg ref SA60007. The modification for which this permission is sought comprise of a single storey extension , of 669.17sqm gross floor area , to the south of the permitted hotel to include extended function room, kitchen residents lounge and associtated w.c facilities, service area, circualtion space and storeage areas extension to foyer area, of 72 sqm gross floor area, at the permitted hotel main entrance at ground floor level only and associated amendments to the layout of the south eastern corner of th ehotel carpark to accomodate the proposed hotel extension. These modifications result in a total hotel gross floor area of 8314.15sqm (7.572.98sqm previously permitted under reg ref SA40505)with the total number of 244 car parking spaces (195 previously permitted under Reg Ref SA40505) |
sa60019 |
DECISION MADE |
PERMISSION |
R |
30/01/2006 Monday |
David & Helen Barry |
Dollardstown Beauparc Navan, Co. Meath |
erection of entrance, new house, double domestic garage, septic tank and percolation area |
sa60030 |
WITHDRAWN |
PERMISSION |
|
01/02/2006 Wednesday |
McGarrell Reilly |
Gormanston Co. Meath
|
a retail warehouse development comprising 1 no. Anchor Unit Measuring 4,450 sq.m.(gross)and 2 no. retail warehouse units each measuring 700sq.m.(gross).The total gross floor area of the development is 8,058sq.m.The development will also include car parking, extension of access road currently under construction under Reg: Ref:SA/40505 as may be modified by the concurrent application under Reg: Ref:SA/60007, public & service entrances, internal roads and all associated site and development works and landscaping. |
SA110866 |
APPLICATION FINALISED |
EXTENTION OF DURATION |
C |
16/09/2011 Friday |
McGarrell Reilly Contractors |
Gormanston Stamullen Co Meath |
EXTENSION OF DURATION OF PLANNING PERMISSION SA60232 - Construction of a warehouse development to comprise of 2 no. blocks of incubator units (4,832sqm gross floor areas each) subdivided into 12 no. units total of 24 no. incubator units provided; 1 no. warehouse unit of 3,960sqm gross floor areas and 1 no. warehouse unit of 5,909sqm gross floor area. Warehouse units include ancillary uses including reception areas, w.c. facilities, office and circulation areas at ground floor and part first floor level. The total gross floor area of the proposed development is 19,533sqm. The development also provides for the provision of car-parking; extension of access road permitted under Re. Ref. SA/60007 provision of internal roads and all associated site and development works and landscaping |
SA130251 |
APPLICATION FINALISED |
PERMISSION |
C |
12/04/2013 Friday |
Task Ltd., |
Unit 1 Block 3 City North Business Park Gormanston |
the construction of a mezzanine extension and resulting new fenestration together with a new entrance & reception area |
SA801239 |
APPLICATION FINALISED |
PERMISSION |
C |
25/04/2008 Friday |
McGarrell Reilly Contractors Ltd |
Gormanston Co. Meath |
the construction of an ESB substation, the proposed ESB substation has a total floor area of approximately 26 sq m |