Planning Application: 2060 (Kildare County Council )
File Number:
2060
Application Type:
RETENTION
Planning Status:
APPEALED FINANCIAL
Received Date:
28/01/2020
Decision Due Date:
23/03/2020
Validated Date:
28/01/2020
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
23/03/2020
Leave to Appeal:
Appeal Date:
09/06/2020
Commenced Date:
Submissions By:
02/03/2020
Applicant Details
Applicant name:
EFIV Irish Property ICAV
Applicant Address:
Phone Number:
Fax Number:
23945542
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
The proposed development specifically relates to Building No. 3 and Building No. 4 located to the north-east of the centre of the site. (No alteration to the balance of the development is sought by this Application). The development for which retention permission is sought consists of: the change of use of Building No. 3 from its permitted warehouse use (Reg. Ref. 95/923) to manufacturing use (4,421 sq. m gross floor area including ancillary offices at ground floor and first floor level); and the change of use of part of Building No. 4 from its permitted manufacturing use (Reg. Ref. 95/923) to office use (9,002 sq. m gross floor area ). The development for which retention permission is sought also consists of: the provision of ancillary office space at first floor level within Building No. 4 (246 sq. m gross floor area); and all other associated site development works above and below ground. The site is principally bounded by; Barnhall Road to the north; Celbridge Road to the east; Barnhall Rugby Football Club to the south; and by grounds associated with Castletown House to the west
Development Address:
At a site of c. 80.56 hectares, , at Liffey Business Campus (formerly known as the Hewlett Packard Campus),, Barnhall Road, , Leixlip, Co. Kildare.
Architect Name:
Tony Fennessy (RKD Architects)
Location Key:
LEIXLIP
Electoral Division:
Planner:
Louise Murphy
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Bar Code 23945542
Decision
Decision Date:
23/03/2020
Manager Order:
CE28171
Decision Type:
Conditional
Number of Conditions:
6
Grant Date:
20/09/2020
Grant Managers Order #:
Section 47
Apply?:
No
Part 5
Apply?:
No
Expiry Date:
19/09/2025
Decision Description:
The proposed development specifically relates to Building No. 3 and Building No. 4 located to the north-east of the centre of the site. (No alteration to the balance of the development is sought by this Application). The development for which retention permission is sought consists of: the change of use of Building No. 3 from its permitted warehouse use (Reg. Ref. 95/923) to manufacturing use (4,421 sq. m gross floor area including ancillary offices at ground floor and first floor level); and the change of use of part of Building No. 4 from its permitted manufacturing use (Reg. Ref. 95/923) to office use (9,002 sq. m gross floor area ). The development for which retention permission is sought also consists of: the provision of ancillary office space at first floor level within Building No. 4 (246 sq. m gross floor area); and all other associated site development works above and below ground. The site is principally bounded by; Barnhall Road to the north; Celbridge Road to the east; Barnhall Rugby Football Club to the south; and by grounds associated with Castletown House to the west
the change of use of the existing and permitted (Reg. Ref:. 95/923) Ancillary Production Support Office associated with part of Building No. 2 to a standalone independent Office use including break room and tea station (c. 1,139sqm). The proposed development specifically relates to Building No. 2 located to the north-east of the centre of the site. (No alteration to the balance of the development is sought by this Application.) The site is principally bounded by: Barnhall Road to the north; Celbridge Road to the east; Barnhall Rugby Football Club to the south; and by grounds associated with Castletown House to the west. At a site of c.80.56 hectares at Liffey Business Campus (formerly known as the Hewlett Packard Campus)
development of 4 No. 20 kV ESB double substations at four sites of c. 591 sqm in total (Site 1, c. 138 sqm adjacent to Building 4; Site 2, c. 138 sqm adjacent to Building 2 and Building 5; Site 3, c. 138 sqm adjacent to Building 5; and Site 4, c. 177 sqm partially within Building 9, at the Kildare Innovation Campus (formerly known as the Hewlett Packard Campus) Barnhall Road, Leixlip, Co. Kildare. The wider Kildare Innovation Campus is c. 80 hectares. The wider Campus is principally bounded by: Barnhall Road to the north; Celbridge Road to the east; Barnhall Rugby Football Club to the south; and grounds associated with Castletown House to the west. The proposed development will consist of: the construction of 3 No. standalone ESB double substations and associated LV switch rooms (Substations No. 1-3) of c. 3m in height, c. 4.8m in depth, and c. 17.8m in width, with an individual gross floor area of 57.5 sqm; and all associated works above and below ground. Substation No. 4 (gross floor area of 57.5 sqm) will include: internal alterations to the existing Campus Building No. 9; associated LV switch rooms; the removal of existing louvre and replacement with substation access doors on the southeast elevation; access path; and all associated works above and below ground. The cumulative gross floor area of the development will be 230 sqm