Planning Application: 18453 (Kildare County Council )
File Number:
18453
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
23/04/2018
Decision Due Date:
28/10/2018
Validated Date:
23/04/2018
Invalidated Date:
Further Info Requested:
14/06/2018
Further Info Received:
03/09/2018
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
26/10/2018
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Kilsaran Concrete
Applicant Address:
Phone Number:
Fax Number:
25176573 & 25176574
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
(i) establishment of an inert soil waste recovery facility to provide for the importation of approximately 1,200,000 tonnes of natural inert waste materials, principally excess soil, stone and / or broken rock to backfill the pit void to former ground level and improve lands currently in agricultural use. The development will be carried out on a phased basis and will be completed within 8 years; (ii) share use, with the existing Kilsaran concrete manufacturing and waste facilities, of existing site and services infrastructure including site office, staff welfare facilities, weighbridge (with dedicated office), wheelwash, hardstand areas, fuel storage tanks and site access; (iii) use of section of existing concrete block curing shed as a waste inspection and quarantine facility; and (iv) temporary stockpiling of topsoil pending re-use as cover material for final restoration of the site. The proposed development requires a waste licence from the Environmental Protection Agency. An Environmental Impact Statement (now referred to as an Environmental Impact Assessment Report (EIRA)) will be submitted
Development Address:
Halverstown, Kilcullen, Co. Kildare
Architect Name:
Location Key:
HALVERSTOWN KILCULLEN
Electoral Division:
Planner:
John O'Hara
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
26/10/2018
Manager Order:
CE20398
Decision Type:
Conditional
Number of Conditions:
23
Grant Date:
04/12/2018
Grant Managers Order #:
CE20398
Section 47
Apply?:
No
Part 5
Apply?:
No
Expiry Date:
03/12/2023
Decision Description:
(i) establishment of an inert soil waste recovery facility to provide for the importation of approximately 1,200,000 tonnes of natural inert waste materials, principally excess soil, stone and / or broken rock to backfill the pit void to former ground level and improve lands currently in agricultural use. The development will be carried out on a phased basis and will be completed within 8 years; (ii) share use, with the existing Kilsaran concrete manufacturing and waste facilities, of existing site and services infrastructure including site office, staff welfare facilities, weighbridge (with dedicated office), wheelwash, hardstand areas, fuel storage tanks and site access; (iii) use of section of existing concrete block curing shed as a waste inspection and quarantine facility; and (iv) temporary stockpiling of topsoil pending re-use as cover material for final restoration of the site. The proposed development requires a waste licence from the Environmental Protection Agency. An Environmental Impact Statement (now referred to as an Environmental Impact Assessment Report (EIRA)) will be submitted
Inert soil & stone / construction and demolition waste recovery facility as revised by significant further information consisting of the lifetime of the development being for a 6 year period