Planning application details ref: 2250813 Donegal County Council

100%100% Complete (warning)

Planning Application: 2250813 (Donegal County Council )
File Number: 2250813
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 11/05/2022 Decision Due Date: 18/04/2023
Validated Date: 11/05/2022 Invalidated Date:
Further Info Requested: 30/06/2022 Further Info Received: 22/02/2023
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 14/04/2023
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By: 28/03/2023

Applicant Details

Applicant name: CRONALAGHT WINDFARM LIMITED
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: (1) REMOVAL OF THE EXISTING 8 NO. 600 AND 660 KILOWATT (KW) TURBINES AND REPLACEMENT WITH 3 NO. 4.5 MEGAWATT TURBINES HAVING AN OVERALL MAXIMUM HEIGHT OF 150M CONSISTING OF A BLADE DIAMETER OF 136M AND A HUB HEIGHT OF 82M. THE DEVELOPMENT WILL ALSO CONSIST OF THE ASSOCIATED TURBINE HARDSTANDS AND FOUNDATIONS, UPGRADING OF C.910M OF EXISTING SITE ACCESS TRACK, PROVISION OF C.799M OF NEW SITE ACCESS TRACK, CONSTRUCTION OF A NEW 38KV SUBSTATION AND 2 NO. JOINT BAYS, DEVELOPMENT OF A NEW BORROW PIT, TEMPORARY CONSTRUCTION COMPOUND, SITE DRAINAGE NETWORK, THE REMOVAL AND RESTORATION OF C.600M OF EXISTING SITE TRACK, INTERNAL WIND FARM UNDERGROUND POWER AND COMMUNICATIONS CABLING, CONNECTION TO THE NATIONAL ELECTRICITY NETWORK BY JOINING TO EXISTING GRID CONNECTIONS PRIOR TO LEAVING THE SITE AND ALL ASSOCIATED SITE DEVELOPMENT AND ANCILLARY WORKS. THIS APPLICATION IS SEEKING A TEN YEAR PERMISSION AND A 40 YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING OF THE WIND FARM. THIS APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ACCESSMENT REPORT (EIAR) & A NATURA IMPACT STATEMENT (NIS)
Development Address: MEENDERRYGAMPH, GWEEDORE, CO. DONEGAL
Architect Name: Location Key: MEENDERRYGAMP
Electoral Division: Magheraclogher Planner: Aideen Quinn
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Yes Comments:

Decision

Decision Date: 14/04/2023 Manager Order: 2023PH0838
Decision Type: Conditional Number of Conditions: 24
Grant Date: 17/05/2023 Grant Managers Order #: 2022PH0838
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 16/05/3033
Decision Description: (1) REMOVAL OF THE EXISTING 8 NO. 600 AND 660 KILOWATT (KW) TURBINES AND REPLACEMENT WITH ERECTION OF 3 NO. 4.5 MEGAWATT TURBINES HAVING AN OVERALL MAXIMUM HEIGHT OF 150M CONSISTING OF A BLADE DIAMETER OF 136M AND A HUB HEIGHT OF 82M. THE DEVELOPMENT WILL ALSO CONSIST OF THE ASSOCIATED TURBINE HARDSTANDS AND FOUNDATIONS, UPGRADING OF C.910M OF EXISTING SITE ACCESS TRACK, PROVISION OF C.799M OF NEW SITE ACCESS TRACK, CONSTRUCTION OF A NEW 38KV SUBSTATION AND 2 NO. JOINT BAYS, DEVELOPMENT OF A NEW BORROW PIT, TEMPORARY CONSTRUCTION COMPOUND, SITE DRAINAGE NETWORK, THE REMOVAL AND RESTORATION OF C.600M OF EXISTING SITE TRACK, INTERNAL WIND FARM UNDERGROUND POWER AND COMMUNICATIONS CABLING, CONNECTION TO THE NATIONAL ELECTRICITY NETWORK BY JOINING TO EXISTING GRID CONNECTIONS PRIOR TO LEAVING THE SITE AND ALL ASSOCIATED SITE DEVELOPMENT AND ANCILLARY WORKS. THIS APPLICATION IS SEEKING A TEN YEAR PERMISSION AND A 40 YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING OF THE WIND FARM. THIS APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ACCESSMENT REPORT (EIAR) & A NATURA IMPACT STATEMENT (NIS)

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: