0425 |
INCOMPLETED APPLICATION |
PERMISSION |
|
08/01/2004 Thursday |
EDENDERRY POWER LIMITED |
BALLYKILLEEN CLONBULLOGUE EDENDERRY |
MATERIAL CHANGE OF USE OF THE ELECTRICITY GENERATING STATION FROM USE AS A POWER STATION FOR THE GENERATION OF ELECTRICAL POWER STATION FROM THE COMBUSTION OF PEAT, TO USE AS A POWER STATION AND A WASTE RECOVERY FACILITY FOR THE GENERATION OF ELECTRICAL POWER FROM THE COMBUSTION OF A MIX OF FUELS INCLUDING BIOMASS IN THE FORM OF WOOD MATERIAL AND RECOVERED (TREATED) MEAT AND BONE MEAL |
04210 |
APPEALED |
PERMISSION |
C |
13/02/2004 Friday |
EDENDERRY POWER LIMITED |
BALLYKILLEEN CLONBULLOGUE EDENDERRY |
MATERIAL CHANGE OF USE OF THE ELECTRICITY GENERATING STATION FROM USE AS A POWER STATION FOR THE GENERATION OF ELECTRICAL POWER STATION FROM THE COMBUSTION OF PEAT, TO USE AS A POWER STATION AND A WASTE RECOVERY FACILITY FOR THE GENERATION OF ELECTRICAL POWER FROM THE COMBUSTION OF A MIX OF FUELS INCLUDING BIOMASS IN THE FORM OF WOOD MATERIAL AND RECOVERED (TREATED) MEAT AND BONE MEAL |
11113 |
APPLICATION FINALISED |
PERMISSION |
C |
28/04/2011 Thursday |
EDENDERRY POWER LIMITED |
BALLYKILLEEN CLONBULLOGUE EDENDERRY |
DEVELOPMENT WHICH WILL CONSIST OF A 14,750m2 (1.48ha) CONCRETE SLAB FOR THE STORAGE OF BIOMASS, WHICH IN THE CONTEXT OF THIS APPLICATION REFERS TO ENERGY CROPS (PRIMARILY WILLOW & MISCANTHUS), FORESTRY RESIDUES, WOODCHIPS AND PULP WOOD ONLY. A FULL RETENTION OIL INTERCEPTOR, SETTLEMENT TANKS, AND ASSOCIATED WORKS WILL COLLECT RAIN WATER RUNOFF FROM THE SLAB FOR DIVERSION INTO THE EXISTING SURFACE WATER MANAGEMENT SYSTEM THE OPERATION OF WHICH IS INCORPORATED INTO THE EXISTING IPPC LICENCE IN FORCE AT THE FACILITY. A 1,700m3 STORAGE SILO WILL BE ERECTED FOR THE STORAGE OF DRY BIOMASS, WHICH IN THE CONTEXT OF THIS APPLICATION REFERS TO AGRICULTURAL RESIDUES OF VEGETAL ORIGIN AND DRY WOOD PELLETS ONLY. AN EMBANKMENT, WITH AN AREA OF 6,750m2 (0.68ha) WILL BE CONSTRUCTED ALONG THE NORTH WESTERN BOUNDARY OF THE FACILITY USING THE MATERIAL EXCAVATED DURING THE CONSTRUCTION OF THE CONCRETE SLAB, THE EMBANKMENT WILL BE LANDSCAPED TO COMPLIMENT THE EXISTING HEDGEROWS ON THE SOUTH WESTERN BOUNDARY. PERMISSION IS ALSO SOUGHT TO ACCEPT 100kt PER ANNUM OF BIOMASS (AS DEFINED ABOVE) IN ADDITION TO THAT ALREADY PERMITTED UNDER PLANNING GRANT PL 19.211173 FOR USE IN CO-FUELLING, THIS MATERIAL WILL BE TRANSPORTED BY ROAD AND REQUIRES PERMISSION FOR THE DELIVERY OF TWENTY EIGHT LOADS PER DAY IN ADDITION TO THOSE ALREADY PERMITTED UNDER PLANNING GRANT PL.19.211173. THE APPLICATION RELATES TO DEVELOPMENT THAT IS FOR THE PURPOSES OF AN ACTIVITY IN RELATION TO WHICH AN INTEGRATED POLLUTION PREVENTION AND CONTROL LICENCE UNDER PART IV OF THE ENVIRONMENT PROTECTION AGENCY ACT, 1992 AS AMENDED, IS REQUIRED. |
1372 |
APPLICATION FINALISED |
PERMISSION |
C |
30/04/2013 Tuesday |
EDENDERRY POWER LIMITED |
BALLYKILLEEN CLONBULLOGUE CO. OFFALY |
THE CONTINUED USE AND OPERATION OF THE PREVIOUSLY PERMITTED PEAT AND BIOMASS CO-FIRED POWER PLANT IN THE TOWNLAND OF BALLYKILLEEN, CLONBULLOGUE, CO. OFFALY; THEREBY POSTPONING REMOVAL OF THE ELECTRICITY GENERATING STATION IN CONTINUATION WITH THE GRANT OF PLANNING PERMISSIONS (OFFALY COUNTY COUNCIL PLANNING REGISTER REFERENCE NUMBER PL2/98/437 / AN BORD PLEANÁLA REFERENCE PL.19.107858 AND OFFALY COUNTY COUNCIL PLANNING REGISTER REFERENCE NUMBER PL2/04/210 / AN BORD PLEANÁLA REFERENCE PL.19.211173). NO NEW STRUCTURES ARE PROPOSED AS PART OF THIS APPLICATION AND EPL IS NOT PROPOSING ANY CHANGE TO EXISTING OPERATIONS, FUEL INPUTS OR EMISSION LIMIT VALUES AT THE FACILITY AS PART OF THIS APPLICATION. THE APPLICATION RELATES TO DEVELOPMENT (THE CONTINUED USE AND OPERATION OF THE PEAT AND BIOMASS CO-FIRED POWER PLANT) THAT IS AN ACTIVITY IN RELATION TO WHICH AN INTEGRATED POLLUTION PREVENTION AND CONTROL (IPPC) LICENCE UNDER PART IV OF THE ENVIRONMENTAL PROTECTION AGENCY ACT, 1992 AS AMENDED, IS REQUIRED. THE POWER PLANT CURRENTLY OPERATES UNDER AN ENVIRONMENTAL PROTECTION AGENCY IPPC LICENCE (REGISTER REFERENCE NUMBER P0482-04) FOR THE ABOVE MENTIONED ACTIVITY. NO CHANGES TO THIS EXISTING IPPC LICENCE ARE PROPOSED AS A CONSEQUENCE OF THIS PLANNING APPLICATION. AN ENVIRONMENTAL IMPACT STATATEMENT (EIS) HAS BEEN PREPARED IN RESPECT OF THIS APPLICATION. THIS EIS HAS BEEN SUBMITTED TO THE PLANNING AUTHORITY WITH THE APPLICATION. THE E.I.S. WILL BE AVAILABLE FOR INSPECTION OR PURCHASE AT A FEE NOT EXCEEDING THE REASONABLE COST OF MAKING A COPY DURING OFFICE HOURS AT THE OFFICES OF THE RELEVANT PLANNING AUTHORITY |
14116 |
INCOMPLETED APPLICATION |
PERMISSION |
|
23/05/2014 Friday |
EDENDERRY POWER LIMITED |
BALLYKILLEEN EDENDERRY CO. OFFALY |
A FEEDSTOCK HANDLING SYSTEM THAT WILL ENHANCE THE EXISTING CONTROL AND METERING SYSTEM ON SITE. THE DEVELOPMENT WILL CONSIST OF A COVERED FEEDSTOCK RECEIVING STATION WITH A CAPACITY OF 400 M3 ('HOPPER') WITH ASSOCIATED CONCRETE SLAB. THE DEVELOPMENT WILL ALSO INCLUDE A SCREEN HOUSE FOR THE REMOVAL OF FERROUS AND OVERSIZE MATERIAL, AS WELL AS ASSOCIATED QUALITY CONTROL SAMPLING EQUIPMENT, AND INCLINE AND BY PASS CONVEYORS OF 688 M2 TO TIE INTO THE EXISTING FEEDSTOCK STORAGE AND HANDLING SYSTEM. THE APPLICATION RELATES TO DEVELOPMENT THAT IS FOR THE PURPOSES OF AN ACTIVITY REQUIRING AN INTEGRATED POLLUTION PREVENTION AND CONTROL LICENCE UNDER PART IV OF THE ENVIRONMENT PROTECTION AGENCY ACT, 1992 AS AMENDED |
14144 |
APPLICATION FINALISED |
PERMISSION |
C |
07/07/2014 Monday |
EDENDERRY POWER LIMITED |
BALLYKILLEEN EDENDERRY CO. OFFALY |
A FEEDSTOCK HANDLING SYSTEM THAT WILL ENHANCE THE EXISTING CONTROL AND METERING SYSTEM ON SITE. THE DEVELOPMENT WILL CONSIST OF A COVERED FEEDSTOCK RECEIVING STATION WITH A CAPACITY OF 400M3 ('HOPPER') WITH ASSOCIATED CONCRETE SLAB. THE DEVELOPMENT WILL ALSO INCLUDE A SCREEN HOUSE FOR THE REMOVAL OF FERROUS AND OVERSIZE MATERIAL, AS WELL AS ASSOCIATED QUALITY CONTROL SAMPLING EQUIPMENT, AND INCLINE AND BY PASS CONVEYORS OF 688M2 TO TIE INTO THE EXISTING FEEDSTOCK STORAGE AND HANDLING SYSTEM. THE APPLICATION RELATES TO DEVELOPMENT THAT IS FOR THE PURPOSES OF AN ACTIVITY REQUIRING AN INTEGRATED POLLUTION PREVENTION AND CONTROL LICENSE UNDER PART IV OF THE ENVIRONMENTAL PROTECTION AGENCY ACT, 1992 AS AMENDED |
15129 |
APPLICATION FINALISED |
PERMISSION |
C |
19/05/2015 Tuesday |
EDENDERRY POWER LIMITED (EPL) |
BALLYKILLEEN EDENDERRY CO. OFFALY |
THE EXTENSION OF THE CONTINUED USE AND OPERATION, UNTIL THE END OF 2030, OF THE PREVIOUSLY PERMITTED PEAT AND BIOMASS CO-FIRED POWER PLANT CURRENTLY EXISTING AND OPERATING; THEREBY POSTPONING REMOVAL OF THE ELECTRICITY GENERATING STATION REQUIRED UNDER THE GRANT OF PLANNING PERMISSIONS (OFFALY COUNTY COUNCIL REFERENCE PL2/98/437 / AN BORD PLEANÁLA REFERENCE PL19.107858 AND OFFALY COUNTY COUNCIL REFERENCE PL2/04/210 / AN BORD PLEANÁLA REFERENCE PL19.211173). NO NEW STRUCTURES ARE PROPOSED AS PART OF THIS APPLICATION AND EPL IS NOT PROPOSING ANY CHANGE TO EXISTING OPERATIONS, FUEL INPUTS OR EMISSION LIMIT VALUES AT THE FACILITY AS PART OF THIS APPLICATION.
THE APPLICATION RELATES TO DEVELOPMENT (THE CONTINUED USE AND OPERATION OF THE PEAT AND BIOMASS CO-FIRED POWER PLANT) THAT IS AN ACTIVITY IN RELATION TO WHICH AN INDUSTRIAL EMISSIONS (FORMERLY INTEGRATED POLLUTION PREVENTION AND CONTROL (IPPC)) LICENCE UNDER PART IV OF THE ENVIRONMENTAL PROTECTION AGENCY ACT, 1992 AS AMENDED, IS REQUIRED.
THE POWER PLANT CURRENTLY OPERATES UNDER AN ENVIRONMENTAL PROTECTION AGENCY INDUSTRIAL EMISSIONS (FORMERLY IPPC) LICENCE (REGISTER REFERENCE NUMBER P0482-04) FOR THE ABOVE MENTIONED ACTIVITY. NO CHANGES TO THIS EXISTING IE/IPPC LICENCE ARE PROPOSED AS A CONSEQUENCE OF THIS PLANNING APPLICATION.
AN ENVIRONMENTAL IMPACT STATEMENT (E.I.S.) AND A NATURA IMPACT STATEMENT (N.I.S.) HAVE BEEN SUBMITTED WITH THIS PLANNING APPLICATION.
|
98437 |
DECISION MADE |
PERMISSION |
C |
28/05/1998 Thursday |
EDENDERRY POWER LTD |
BALLYKILLEEN EDENDERRY
|
PEAT POWER 120 MW ELECTRICITY GENERATING STATION |
98922 |
APPLICATION FINALISED |
PERMISSION |
C |
03/11/1998 Tuesday |
ELECTRICITY SUPPLY BOARD |
BALLYKILLEEN CO KILDARE
|
110 KV OVERHEAD TRANSMISSION LINE LOOP SERVING PROPOSED EUROPEAT 1 POWER STATION |