File No |
Status |
Type |
Decision |
ReceivedDate |
Name |
Development Address |
Description |
0281 |
APPLICATION FINALISED |
PERMISSION |
C |
28/02/2002 Thursday |
E.S.B. |
Lanesboro Generating Stat Aghamore Td. Lanesboro, Co. Longford |
New 110 KV Station Control Building, including additional control cable ducting, realignment and replacement of the existing compoung fence, and replacement of switchgear, within the boundary fence |
1938 |
WITHDRAWN |
PERMISSION |
|
13/02/2019 Wednesday |
Electricity Supply Board |
Aghamore & Lanesborough Derraghan More & Derraghan Beg Co. Longford |
development at the existing electricity generating station - known as Lough Ree Power (LRP) station, located in the townlands of Aghamore and Lanesborough in the settlement of Lanesborough (Lanesboro), Co. Longford, Eircode N39 E180; and at an existing ash disposal facility (ADF) located in the townlands of Derraghan More and Derraghan Beg, Co. Longford. (Full Description scanned / attached) |
19188 |
WITHDRAWN |
PERMISSION |
|
11/07/2019 Thursday |
Electricity Supply Board |
Aughamore & Lanesborough Derraghan More & Derraghan Beg Co. Longford |
development at the existing electricity generating station - known as Lough Ree Power (LRP) station, located in the townlands of Aghamore and Lanesborough in the settlement of Lanesborough (Lanesboro), Co. Longford, Eircode N39 E180; and at an existing ash disposal facility (ADF) located in the townlands of Derraghan More and Derraghan Beg, Co. Longford. (Full Description scanned / attached) |
19201 |
APPLICATION FINALISED |
PERMISSION |
C |
29/07/2019 Monday |
EirGrid Plc |
Aghamore Lanesborough Longford |
the development will consist of the redevelopment of the existing Lanesboro 110kV AIS substation with a new 110 kV Gas Insulated Switchgear (GIS) substation. The 110 kV GIS substation redevelopment will comprise of the following elements: (i) A110 kV GIS substation contained within a building with a gross floor area of approximately 1,470m2 (54m x 15m) and a height of 15m. Associated development within the footprint of the GIS substation development will include: 6 no. lightning rods of approximately 3m in height located on the parapet of the GIS Building: a Distribution System Operator (DSO) compound (approximately 30m2); an internal circulation road of approximately 245m in length and 5m in width, 12 no. car parking spaces; underground stormwater attenuation tank; underground foul wastewater pumping station and all associated site development and landscaping works. The substation will be bounded by a palisade fence 2.6m in height and bounded with a property fence 1.4m in height; (ii) The modification of 8 no. existing 110 kV underground circuits which will be re-routed into the new 110 kV GIS substation: Sliabh Bawn-Lanesboro underground circuit, Cloon-Lanesboro underground circuit, Athlone-Lanesboro underground circuit, Richmond 1-Lanesboro underground circuit, Richmond 2-Lanesboro underground circuit, Lough Ree Power T104-Lanesboro underground circuit, T141-Lanesboro underground circuit and Mullingar-Lanesboro underground circuit. Associated development includes the construction of 3 no. underground joint bays; 1 no. gantry tower (footpring of 30.2m2 and a height of 12.5m); 1 no. Line Cable Interface Mast (footprint of 123m2 and the height of 20.7m) and all associated and ancillary transmission infrastructure. (iii) The construction of a Landowner access road of approximately 91m in lenghth and 6m in width |
2275 |
APPLICATION FINALISED |
PERMISSION |
C |
01/04/2022 Friday |
Electricity Supply Board |
Aughamore And Lanesborough Co Longford |
development at the 13.1 Ha site known as 'Lough Ree Power (LRP) Station' located in Lanesborough (Lanesboro), in the townlands of Aghamore and Lanesborough, Eircode N37E180; in County Longford. The development will consist of the demolition of the existing LRP station (as approved under Longford County Council reg.ref 01/115 ' An Board Pleanala Ref. PL14.125540 and all subsequent permissions);and the development and operation of electricity grid services - namely a battery energy storage system (BESS) and a Synchronous Condenser (Sync Con). The proposed development comprises two distinct phases of activity - the initial demolition and site reinstatement (Phase 1); following by construction and operation of the new BESS and Sync Con (phase 2). Phase 1 comprises the demolition of existing site structures (with a total footprint of c. 11.195sq.m. and a total gross floor area of c. 20,000 sq.m) including the former LRP station (boiler house, turbine house, bag filter house and associated 80 m high stack); the intermediate peat storage building and associated fuel management system; and ancillary buildings including, electrical building, tippler building and associated control room and office, the screening building, lorry uploading building, water treatment plant building, offices building, laboratory building, workshop and maintenance buildings, oil pumphouse, electrics rooms, railway/locomotive service building, cooling water pump house and sewage/foul water treatment facility. All buildings and structures (including storage tanks and vessels) will be demolished to ground level, with below ground voids filled. Existing hard standing surfac3es (e.g. building ground floor concrete slabs, tarmacadam surfaces, concrete footpaths and road kerbs) will remain in site; and the site will be reinstated and secured with boundary gates and fences, etc. Associated with the demolition activity there will be on-site crushing of material using mobile machinery for the purposed of disposal and/or material re-use. Phase 2 comprises the proposed development of the BESS, Sync Con; and all associated development (Full description scanned/attached) |
2360056 |
APPLICATION FINALISED |
PERMISSION |
C |
19/06/2023 Monday |
EirGrid Plc |
Existing Lanesboro Air Insulted Switchgear Substation and site of the former Lanesborough Power Station townlands of Aghamore and Lanesborough Lanesborough, County Longford |
1. Construction of a Gas Insulated Switchgear (GIS) compound measuring
approximately 92.8m by 90.5m. The proposed GIS compound will be raised to a ground level of 1.2m higher than the existing ground level at the site, and will
comprise: (i) GIS building with an approximate gross floor space 1624.1m2 and height of 15m (in addition, 6 no. lightning protection rods, approximately 3m in height, are located on the parapet of the GIS building); (ii) An internal access track measuring approximately 245m in length and 5m in width, 15 no. car parking spaces; underground stormwater attenuation tank; underground foul wastewater pumping station and all associated site development and landscaping works; and
(iii) The substation compound will be bounded by a palisade fence 2.6m in height and further enclosed by a property fence measuring 1.4m in height.
2. The proposed development will also consist of the redevelopment of the existing AIS 110 kV substation, comprising the following: (i) Decommissioning of the 110 kV AIS busbar and 110 kV primary plant within the existing 110 kV AIS substation; (ii)The modification of 8 no. existing 110 kV underground circuits which will be re-routed into the new 110 kV GIS substation; and, (iii) Construction of 3no. underground joint bays; 1 no. new gantry tower (approximate footprint of 30.2m2 and a height of 12.5m); 1 no. new Line Cable Interface Mast (approximate footprint of 123m2 and a height of 20.7m); removal of the existing 110 kV OHL tower and section of cable which extends to the proposed Line Cable Interface Mast and all associated and ancillary transmission infrastructure. 3. Construction of a Distribution System Operator (DSO) compound measuring approximately 30m2; 4. Construction of a landowner access road (hardcore surfacing) of approximately 91m in length and 6m in width; and, 5. All ancillary site development works to facilitate the proposed development including geotechnical and geo-environmental ground investigations, site preparation works, site clearance and levelling, site drainage and associated outfall headwall to facilitate discharge to the River Shannon, temporary construction compounds and landscaping |
2360108 |
APPLICATION FINALISED |
PERMISSION |
C |
14/08/2023 Monday |
EirGrid plc |
Lanesborough Town and Aghamore Townland County Longford |
the proposed development within Co. Longford will comprise:
• the replacement (“restringing”) of the existing overhead line circuit conductor wires with a new higher capacity conductor including installation of a new fibre communication connection;
• the retention and refurbishment, steel member replacement, painting and foundation strengthening of the one retained end mast EM1, including the replacement of hardware and fittings, replacement of vibration dampers, and replacement of insulators at EM1;
• The cutting of timber / vegetation;
• all associated works within the existing Lanesboro 110kV substation to accommodate the uprated 110kV OHL including uprating of the Sliabh Bawn bay in Lanesboro 110kV substation and alterations to existing hardware; and
• other temporary associated and ancillary site development works required for the purpose of the uprate of the existing circuit, including construction compounds, silt traps, silt fences, stone tracks, ground protection mats, infrastructure crossing support systems and temporary watercourse crossings |