Planning application details ref: 22275

100%100% Complete (warning)



File Number 22275
Application Type PERMISSION Planning Status APPLICATION FINALISED
Received Date 08/12/2022 Decision Due Date 21/04/2023
Validated Date 08/12/2022 Invalidated Date
Further Info Requested 02/02/2023 Further Info Received 24/03/2023
Withdrawn Date Extend Date
Decision Type Conditional Decision Date 17/04/2023
Leave to Appeal Appeal Date
Commenced Date Submissions By

Applicant Details

Applicant name Harmony Solar Longford Ltd
Applicant address
Phone Number Fax Number
Corresp. Address

Applicant Details


Proposed Development

Development Description an underground electrical cable and transformer compound which will connect permitted solar farms within the townlands of Middleton, Ballycore, Treanboy, Newtown, Ballynakill, Bunacloy to the national grid via the proposed transformer compound at Lough Ree Power Station (within the townland of Aghamore). The Development will consist of the following components 1) and 2): 1) installation of 110kV:33kV Transformer (TRAFO) Compound on private lands at Lough Ree Power Station, within the townland of Aghamore, with associated equipment including; cable sealing end (CSE) surge arrestor (SA), earth disconnect (ED) current/voltage transformer (CT/VT) house transformer (HT) circuit breaker (CB) 1 x lightening mast (LM) at approx. 8m tall, associated underground cabling connection to the existing 110kV underground cable, diesel generator, security fence, removal of portacabins, use of and realignment of the existing access road and associated works, drainage provision, temporary construction compound and also predevelopment site investigation works. 2) installation of underground 33kV medium Voltage electrical cable with associated ducting primarily on private lands within the townlands of Kilnacarrow, Ballynakill, Cloonkeel, Derryaroge, Cloonbearla, Mount Davys, Cloonbony and Aghamore. 5.77km of the route is located on private lands with0.011km to be located on the L52652 local road and L-11623 local road. The cable installation will include the installation of 7 no. joint bays with associated communication chambers, ancillary development and also pre-development site investigation works. The underground cable is intended to connect the permitted Middleton House Solar Farm (Planning ref: 18/135) and "Middleton House Solar Farm" Bunacloy extension (Planning Ref: 21/225) to the national grid via the proposed transformer compound at Lough Ree Power Station within the townland of Aghamore. Temporary construction compounds to facilitate the installation of the cable will be located along the underground grid connection route. Part of the proposed development site lies within the boundary of Lough Ree Power Station which is licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence Ref. P0610-02). Permission is sought for a period of 10 years
Development Address Kilnacarrow, Ballynakill, Cloonkeel, Derryaroge, Cloonbearla, Mount Davys, Cloonbony, Aghamore, Lanesborough, Co Longford
Architect Name Location Key LANESBORO COUNTY LONGFORD
Electoral Division Planner None
Social Housing Exempt Plan Enforcement #
IPC IPC Licence Required No Waste Licence Required No
Protected Structure No Protected Structure #
Development Name

Proposed Development


Comments

Significant Case Flag Comments

Decision

Decision Date 17/04/2023 Manager Order 30187
Decision Type Conditional Number of Conditions 10
Grant Date 19/05/2023 Grant Managers Order # 30187
Section 47 Apply? Part 5 Apply?
Expiry Date 18/05/2028
Decision Description an underground electrical cable and transformer compound which will connect permitted solar farms within the townlands of Middleton, Ballycore, Treanboy, Newtown, Ballynakill, Bunacloy to the national grid via the proposed transformer compound at Lough Ree Power Station (within the townland of Aghamore). The Development will consist of the following components 1) and 2): 1) installation of 110kV:33kV Transformer (TRAFO) Compound on private lands at Lough Ree Power Station, within the townland of Aghamore, with associated equipment including; cable sealing end (CSE) surge arrestor (SA), earth disconnect (ED) current/voltage transformer (CT/VT) house transformer (HT) circuit breaker (CB) 1 x lightening mast (LM) at approx. 8m tall, associated underground cabling connection to the existing 110kV underground cable, diesel generator, security fence, removal of portacabins, use of and realignment of the existing access road and associated works, drainage provision, temporary construction compound and also predevelopment site investigation works. 2) installation of underground 33kV medium Voltage electrical cable with associated ducting primarily on private lands within the townlands of Kilnacarrow, Ballynakill, Cloonkeel, Derryaroge, Cloonbearla, Mount Davys, Cloonbony and Aghamore. 5.77km of the route is located on private lands with0.011km to be located on the L52652 local road and L-11623 local road. The cable installation will include the installation of 7 no. joint bays with associated communication chambers, ancillary development and also pre-development site investigation works. The underground cable is intended to connect the permitted Middleton House Solar Farm (Planning ref: 18/135) and "Middleton House Solar Farm" Bunacloy extension (Planning Ref: 21/225) to the national grid via the proposed transformer compound at Lough Ree Power Station within the townland of Aghamore. Temporary construction compounds to facilitate the installation of the cable will be located along the underground grid connection route. Part of the proposed development site lies within the boundary of Lough Ree Power Station which is licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence Ref. P0610-02). Permission is sought for a period of 10 years

Appeal Details


Appeal Details
Notification Date BP Reference #
Appeal Type File Forward Date
Submission Due Date Submission Sent Date
Appeal Decision Decision Date
Withdrawn Date Dismissed Date