115055 |
APPLICATION FINALISED |
PERMISSION |
C |
25/05/2011 Wednesday |
Bio Agrigas Ltd |
Newdown, The Downs, Mullingar. |
Bio-energy facility containing a Reception Building, Reception Area, Engine room, Pumps and Heat Exchangers, Administration Building containing Office, Staff and Amenity and Changing facilities. Permission is also sought for Tank Farms to include 2 No. Anaerobic Digestors, 2 No. Post Digestion Storage Tanks, 5 No.pre-storage tanks, Gas flare and Gas cleaning vessel. Ancillary facilities will include 1 No. Weighbridge, ESB Substation, Post Digestion Loading Area, Wheel Wash Area, on site Waste Water Treatment System, fencing, gates, New entrance road to proposed N4 Grade Separation Scheme and Internal Roads with all associated works including landscaping, boundaries and services above and below ground. Permission is also sought for temporary Road Access on to the R156 Killucan road from the proposed development during the construction of the new N4 Grade Separation Scheme. The process of Anaerobic Digestion is the subject of an application for a Waste Licence, all of which is described in detail in an accompanying Environmental Impact Statement (EIS). All of the relevant waste recovery activities as per the fourth schedule of the Waste Management Act 1996 -2003, to which this application relates. |
146136 |
APPLICATION FINALISED |
PERMISSION |
C |
13/08/2014 Wednesday |
Thomas Flynn |
Newdown The Downs Mullingar |
Proposed Storage Building for drying and storing Agricrop and Biomass with new site entrance, parking spaces, photo voltaic solar panels and all associated site works and services. |
166184 |
APPLICATION FINALISED |
PERMISSION |
C |
26/07/2016 Tuesday |
Thomas Flynn |
Newdown The Downs Mullingar |
5MW solar farm comprising of approximately 20,000 photovoltaic panels on ground mounted frames within total site area of 9.3 hectares, 5 no. single storey inverter/transformer stations, security fencing, CCTV, access road from existing car park area and all associated ancillary development works. |
206101 |
APPLICATION FINALISED |
PERMISSION |
C |
23/04/2020 Thursday |
Bio Agrigas Ltd |
Newdown The Downs Mullingar |
Bio-energy facility containing a reception building comprising of reception area, engine room, pumps and heat exchangers. Administration building containing office, staff amenity and changing facilities. Permission is also sought for tank farms to include 2 No. anaerobic digesters, 2 No. post digestion storage tanks, 5 no. pre-storage tanks, gas flare and gas cleaning vessel. Ancillary facilities will include 1 No. weighbridge, ESB substation, post digestion loading area, wheel wash area, on site waste water treatment system, fencing, gates, new entrance road to N4 Grade Separation Scheme and internal roads with all associated works including landscaping, boundaries and services above and below ground. The plant will operate as per the conditions of waste licence (REF W0285-01). An Environmental Impact Statement (EIS) has been prepared and accompanies this planning application |