Planning application details ref: 2460313 Tipperary County Council

100%100% Complete (warning)

Planning Application: 2460313 (Tipperary County Council )
File Number: 2460313
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 25/04/2024 Decision Due Date: 10/01/2025
Validated Date: 25/04/2024 Invalidated Date:
Further Info Requested: 12/06/2024 Further Info Received: 05/12/2024
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 11/12/2024
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By:

Applicant Details

Applicant name: Health Service Executive
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: a new energy centre building, generator and fuel storage compounds to the existing services. Works to include the following; (a) the demolition of the existing diesel storage tank and associated concrete bund, removal of existing electrical generator, and associated fencing to the generator compound; (b) a proposed new secured fuel storage compound with associated stone faced walls and new self-bunded fuel storage tank; (c) a proposed new single storey energy centre building containing a new LV switch room, a new transformer room, a new RMU and a new ESB substation; (d) a proposed 2 no. freestanding electrical generators within a new generator compound with an associated timber fence; (e) alterations to the existing site to include for repositioned accessible parking, ramps, footpaths, and landscaping; (f) and all ancillary site works both above and below ground. This is a protected structure
Development Address: Nenagh General Hospital, Tyone Road, Nenagh, Co. Tipperary, E45PT86
Architect Name: Location Key: Tyone Road, Nenagh
Electoral Division: Planner: Olive O'Donnell
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: Yes Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 11/12/2024 Manager Order:
Decision Type: Conditional Number of Conditions: 5
Grant Date: 23/01/2025 Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 22/01/2030
Decision Description: a new energy centre building, generator and fuel storage compounds to the existing services. Works to include the following; (a) the demolition of the existing diesel storage tank and associated concrete bund, removal of existing electrical generator, and associated fencing to the generator compound; (b) a proposed new secured fuel storage compound with associated stone faced walls and new self-bunded fuel storage tank; (c) a proposed new single storey energy centre building containing a new LV switch room, a new transformer room, a new RMU and a new ESB substation; (d) a proposed 2 no. freestanding electrical generators within a new generator compound with an associated timber fence; (e) alterations to the existing site to include for repositioned accessible parking, ramps, footpaths, and landscaping; (f) and all ancillary site works both above and below ground. This is a protected structure

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: