Planning application details ref: 18601545 Tipperary County Council

100%100% Complete (warning)

Planning Application: 18601545 (Tipperary County Council )
File Number: 18601545
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 21/12/2018 Decision Due Date: 12/08/2019
Validated Date: 21/12/2018 Invalidated Date:
Further Info Requested: 21/02/2019 Further Info Received: 18/06/2019
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 09/08/2019
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By:

Applicant Details

Applicant name: Lidl Ireland GmbH
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: the demolition of the former Erin Food Factory, associated buildings and structures as well as works to change the levels of the site. The construction of a supermarket (discount foodstore) with ancillary off licence area and a total gross floor area of 2,268 sq.ms; café/restaurant building with a gross floor area of 193 sq.ms; a three storey office building with a gross floor area of 5,542 sq.ms; ESB substation building; new access arrangements and works to Slievenamon Road (N62) and Clongour Road to provide a lighted junction with all associated works above and below ground together with provision for future access to adjoining lands. The development includes riverside amenities and soft and hard landscaping areas, 305 parking spaces to service the above proposed uses (including 15 mobility impaired spaces and 15 Electric Vehicle charging spaces) and 64 cycle parking spaces; all drainage and underground works; lighting across the entire development; signage for the supermarket. The application is accompanied by a Nature Impact Statement
Development Address: The Former Erin Foods Factory, Slievenamon Road, Clongour, Thurles Town Parks, Thurles
Architect Name: Location Key: SLIEVENEMON ROAD, THURLES
Electoral Division: Planner: ANNE MARIE DEVANEY
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 09/08/2019 Manager Order:
Decision Type: Conditional Number of Conditions: 19
Grant Date: 13/09/2019 Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 12/09/2024
Decision Description: the demolition of the former Erin Food Factory, associated buildings and structures as well as works to change the levels of the site. The construction of a supermarket (discount foodstore) with ancillary off licence area and a total gross floor area of 2,268 sq.ms; café/restaurant building with a gross floor area of 193 sq.ms; a three storey office building with a gross floor area of 5,542 sq.ms; ESB substation building; new access arrangements and works to Slievenamon Road (N62) and Clongour Road to provide a lighted junction with all associated works above and below ground together with provision for future access to adjoining lands. The development includes riverside amenities and soft and hard landscaping areas, 305 parking spaces to service the above proposed uses (including 15 mobility impaired spaces and 15 Electric Vehicle charging spaces) and 64 cycle parking spaces; all drainage and underground works; lighting across the entire development; signage for the supermarket. The application is accompanied by a Nature Impact Statement

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: