Planning application details ref: 221703 Meath CoCo

100%100% Complete (warning)

Planning Application: 221703 (Meath CoCo)
File Number: 221703
Application Type: PERMISSION Planning Status: APPEALED
Received Date: 21/12/2022 Decision Due Date: 01/11/2023
Validated Date: 21/12/2022 Invalidated Date:
Further Info Requested: 22/02/2023 Further Info Received: 18/08/2023
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 31/10/2023
Leave to Appeal: Appeal Date: 27/11/2023
Commenced Date: Submissions By: 11/10/2023

Applicant Details

Applicant name: Albert Developments Ltd
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: The development will consist of Phase 1 of the Boyne Village Enterprise Park, and comprise construction of: 3 no. commercial high-bay warehouse units (each c. 15.81m in height) with ancillary office accommodation as follows: Unit A2 (approx. 2,570 sq. m. gross floor area including 254 sq. m. of reception/office/ancillary areas at ground and first floor levels), Unit A3 (approx. 2,058 sq. m. gross floor area including 200 sq. m. of reception/office/ancillary areas at ground and first floor levels) & Unit A4 (approx. 2,570 sq. m. gross floor area including 254 sq. m. of reception/office/ancillary areas at ground and first floor levels); New road and pedestrian access extending north from the existing LDR 6 distributor road, and a total of 73 No. car-parking spaces and 84 No. bicycle-parking spaces serving the three proposed units; Totem sign at the south-east corner of the site approx. 12.Sm tall providing c. 47.76 sq. m. of internally Illuminated signage; Relocation of existing overhead ESB power lines at the LDR 6 to new underground ducts and provision of new ESB sub-station and switch room accessed from new estate road; Road infrastructure works to the north-east side of the LDR 6 to include new cycle lane, footpath, bus stop lay-by etc.; Planting & landscaping, new boundary treatments; Waste storage units serving each unit. drainage & infrastructure (including temporary foul pumping station) and all other associated works to facilitate the proposed development. A Natura Impact Statement will be submitted to the planning authority with the application. Significant further information/revised plans submitted on this application
Development Address: Ferganstown & Ballymacon & Athlumney, Navan, Co. Meath
Architect Name: Ian Livingstone Location Key: FERGANSTOWN + BALLYM
Electoral Division: Incorrect Icl Voter Recor Planner: Gerard Kellett
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments: Agreed to extend deadline for sub of FI to 21/11/23 - NIS not EIAR

Decision

Decision Date: 31/10/2023 Manager Order: 1653/23
Decision Type: Conditional Number of Conditions: 19
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date:
Decision Description: The development will consist of Phase 1 of the Boyne Village Enterprise Park, and comprise construction of: 3 no. commercial high-bay warehouse units (each c. 15.81m in height) with ancillary office accommodation as follows: Unit A2 (approx. 2,570 sq. m. gross floor area including 254 sq. m. of reception/office/ancillary areas at ground and first floor levels), Unit A3 (approx. 2,058 sq. m. gross floor area including 200 sq. m. of reception/office/ancillary areas at ground and first floor levels) & Unit A4 (approx. 2,570 sq. m. gross floor area including 254 sq. m. of reception/office/ancillary areas at ground and first floor levels); New road and pedestrian access extending north from the existing LDR 6 distributor road, and a total of 73 No. car-parking spaces and 84 No. bicycle-parking spaces serving the three proposed units; Totem sign at the south-east corner of the site approx. 12.Sm tall providing c. 47.76 sq. m. of internally Illuminated signage; Relocation of existing overhead ESB power lines at the LDR 6 to new underground ducts and provision of new ESB sub-station and switch room accessed from new estate road; Road infrastructure works to the north-east side of the LDR 6 to include new cycle lane, footpath, bus stop lay-by etc.; Planting & landscaping, new boundary treatments; Waste storage units serving each unit. drainage & infrastructure (including temporary foul pumping station) and all other associated works to facilitate the proposed development. A Natura Impact Statement will be submitted to the planning authority with the application. Significant further information/revised plans submitted on this application

Appeal Details


Appeal Details
Notification Date: 28/11/2023 BP Reference #: ABP-318533-23
Appeal Type: THIRD PARTY File Forward Date: 06/12/2023
Submission Due Date: 05/02/2024 Submission Sent Date: 05/02/2024
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: