File No |
Staus |
Type |
Decision |
Received Date |
Name |
Development Address |
Description |
1991 |
APPLICATION FINALISED |
PERMISSION |
C |
01/02/2019 Friday |
|
Collinstown, Leixlip, Blakestown, Kellystown, Kilmacredock Lower, Collinstown Industrial Park, Leixlip, |
an extended and revised manufacturing facility (granted under An Bord Pleanála Ref. PL09.248582; Kildare County Council Ref. 16/1229) including reconfigured and extended support buildings, water tanks and yards to provide for additional manufacturing capacity. The development will consist of buildings, site infrastructure and ancillary works, for the manufacture of integrated circuits. A 10 year planning permission is requested. The proposed development comprises: (1) Manufacturing Building Extension to the previously permitted manufacturing building, over four levels (parapet height of 31sqm). The manufacturing extension to the permitted building will have a floor area of circa 109,745sqm.This will include support areas and roof mounted stacks and equipment, ranging in height from 6m to 25m above parapet together with its associated 4 level link building sized 8,160sqm and circa 31m high located to the east of the permitted manufacturing building with minor elevational alterations to the previously permitted manufacturing building. (2) Manufacturing Utility Support Building(s) Revised design and configuration of previously permitted support buildings consisting of: i) A two level boiler and chiller building and associated roof mounted cooling towers, sized 22,188sqm and circa 24.5m high; (ii) A four level water treatment and compressor building, sized circa 11,992sqm and circa 27m high; (iii) A two level waste water treatment building, sized circa 4,974sqm and circa 17m high and a single storey analyser building sized 37sqm and circa 7m high, and its associated single storey electrical building sized 180sqm and circa 7m high; iv) A bulk gas and electrical yard with storage for gasses and liquids with roofed compounds sized 538sqm and circa 6m high and a single storey support building sized 73sqm and circa 6.5m high and an electrical yard housing transformers and 3 No. electrical building sized 446sqm in total and circa 7m high; v) A 4 level structure housing 40 No. emergency generators and their associated stacks circa 21m high and their 3 associated electrical buildings sized 200sqm gross and circa 4.5m high and their associated transformers. All the above buildings have roof mounted equipment and stacks ranging from circa 5m to 18m high. (3) Water Tanks, 8 No. water tanks 38m in diameter and circa 10m high, and a single storey pumphouse sized 840sqm and circa 5m high. (4) Site Works, Building Links and Yard Equipment Extension and revised |
191054 |
APPLICATION FINALISED |
PERMISSION |
C |
23/09/2019 Monday |
|
Collinstown Leixlip Co. Kildare |
(1) Mound The substantial removal of an existing man made earth and stone mound sized approximately 300 metres x 150 metres and up to approximately 18 metres high and approximately 380,000 metres cubed located directly North of Fab 10 and Fab 14. (2) Yard The construction of a yard area housing site supporting functions, utilities and buildings sized 300 metres x 150 metres approximately on the site of the removed mound area, as further described hereunder. (i) Waste Water A waste water tank sized 51 metres by 33 metres and 12 metres high and a yard housing tanks and equipment. (ii) Balance Tank A site waste water (below grade) balance tank sized 35 metres x 25 metres. (iii) Air Separation Unit An Air Separation Unit (ASU) compound and associated 4 no. towers 43 metres high, cooling towers, associated equipment and a single storey compressor building sized 450 square metres and circa 25 metres high, and 2 no. single storey Electrical buildings sized 120 square metres gross and 7 metres high. (iv) Electrical Buildings 4 no. Electrical buildings, all elevated single storey buildings with a gross area of 648 square metres and 6 metres high. (v) Storage Tanks A yard area housing bulk storage tanks for liquid oxygen, waste solvent storage and hydrogen and their associated tanker unloading. (vi) Waste Water Holding Tanks A series of modular waste water holding tanks and associated equipment located in yards with connecting pipebridges. The proposed tanks range from 5 metres high to 20 metres high. (vii) Tanker and Truck Staging Yards A tanker and truck holding and staging yard sized circa 80 x 40 metres located to the North of the proposed development. (3)Site Works The proposed development includes linking pipe-bridges to the Fab 10, Fab 14 and Fab 24 support buildings, site development works and a surface water attenuation tank, site utilities, site lighting, separation walls, roads, landscaping and all associated site works. This application consists of a variation to a previously permitted development for an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act 2003) is required. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) accompany this application. This is a site to which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies. Revised by SFI |
191339 |
APPLICATION FINALISED |
PERMISSION |
C |
03/12/2019 Tuesday |
|
Collinstown, Leixlip, Blakestown, Kellystown Collinstown Industrial Park, |
modifications to the permitted ASU's (Air Separation Units, tank and equipment installations granted as part of the development permitted under An Bord Pleanála Ref. ABP-304672-19 (Kildare County Council Ref. 19/91), including reconfigured site layout of the proposed structures and support plant. The proposed development comprises: Air Separation Units. The proposed development includes positional alterations to the 2no. permitted Air Separation Unit (ASU) compounds, associated towers and compressor buildings. Towers are circa 65 metres high and associated compounds including tanks and equipment are circa 45 metres high and compressor buildings are approximately 20m metres high, all located to the north of the existing Fab 14 building. The ASU compounds also comprise of 2no. compressor buildings each sized 765 square metres approximately and circa 20 metres high with roof mounted plant, equipment and storage and associated 1no. single storey electrical building sized 60 square metres approximately and circa 6 metres high with roof mounted equipment. The proposed development also relates to associated site development works associated equipment housings, yard works and tank bunds, pipe-bridges, and lighting. The application consists of a variation to a previously permitted development for an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act, 2003) is required. A "Natura Impact Statement ("NIS") accompanies this application, and will be available for inspection or purchase at the office of the Planning Authority. This is a site to which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies |
20333 |
APPLICATION FINALISED |
PERMISSION |
C |
31/03/2020 Tuesday |
Intel Ireland Limited |
Collinstown, Leixlip, Blakestown, Kellystown, Collinstown Industrial Park, |
minor modifications to the previously permitted applications An Bord Pleanála Ref. PL09.304672 (Kildare County Council Ref. 19/91) and An Bord Pleanála Ref. PL09.248582 (Kildare County Council Ref. 16/1229). The proposed minor modifications and reconfigurations comprise: (1) Alterations and reconfigurations to roof-mounted service ducting to the permitted Manufacturing Buildings. This will result in an overall elevation height increase ranging between 3 to 6 metres, with an overall maximum increase of 3 metres, including structural framing and fixings. (2) The addition of a steel framed service platform to allow access to 2no. previously permitted flue stacks to the roof of the Waste Water Treatment Building, approximately 6.6 metres wide, 11.5 metres long and approximately 8.6 metres in height from finished roof level. The application also includes a proposed alteration to the existing Silane Pad, to replace exiting pad-mounted gas cylinders with removeable gas trailer. This application consists of a variation to a previously permitted development for an activity for which a license under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act, 2003) is required. This is a site to which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies |
21229 |
APPLICATION FINALISED |
PERMISSION |
C |
26/02/2021 Friday |
Intel Ireland Limited |
Collinstown, Leixlip Blakestown, Kellystown Collinstown Industrial Park |
(1) Modular Storage Unit. A Single storey storage unit, sized approximately 7 metres by 12 metres and 6 metre high, located in the Utilities Yard to the north of the existing Fab10 Support Building. (2) FAB10 Waste Tanks. The installation of 3no. new bunded waste storage tanks, 2no. sized approximately 2.5 metres in diameter and 16.5 metres high, located in the Utilities Yard to north of the existing Fab10 Support Building and 1no. sized approximately 3.7metres in diameter and 15 metres high located to the north of the Fab10 Utilities Yard. (3) Process Support Building Extension. The construction of a two-storey extension to the existing Process Support Building (PSB) sized approximately 20 metres by 11 metres and 14 metres high, located to the north east of the existing Fab 24 Process Support Building. (4) FAB24 and FAB14 Waste Tanks. The installation of 3no. additional waste tanks and associated access platforms and stairways, 1no. sized approximately 9 metres by 10 metres and 7 metres high, located in the Utilities Yard to the north of the existing FAB24 Manufacturing Building and 1no. sized approximately 3 metres high located to the south of existing FAB14 Process Building and 1 no. sized approximately 4.25 metres in diameter and 16 metres high, located to the south of existing FAB14 process Building.(5) Site Works. The proposed development includes linking pipe-bridges to the Fab10 and Fab14 support buildings, site development works, site utilities, site lighting, separation walls, road alterations, landscaping and all associated site works. This application consists of a variation to a previously permitted development for an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act, 2003) is required. A Natura Impact Statement ("NIS") accompanies this application for inspection or purchase at the office of the Planning Authority. This is a site to which the Chemical Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I.209 of 2015) applies |