E.O.D. on Pl. Ref. 08/567. Permission for development on lands (1.425ha). The proposed development is Phase 2 of Galway West District Centre and involves the revision to the previously permitted Phase 2 proposals (Reg. Ref. 06/435, Ref.: Pl.61.222699) and extension of the site to the north that will result in the omission of the previously permitted 4 no. residential blocks (34 no. apartments), 1 no. office and a creche permitted under Reg. Ref.: 06/399. The proposed development comprises the following: - standalone 3-4 storey block located on the northern side of new pedestrian link to Bothar Stiofan comprising: creche at ground floor level (240sq.m) with external play area; management office (247sq.m) at first floor level; 7 no. retail units at ground and first floor levels (8,762sq.m); primary health care facility at second and third floor with associated ground floor lobby/reception area (3,600sq.m) 3 no. restaurant/cafe units at ground and first floor level (976sq.m) located on the northern elevation of Unit 6 (Dunnes Stores) fronting the new pedestrian link. 2 no. ESB substations (58.25sq.m), Car parking will be provided at surface and basement level for 149 no. additional spaces which will be an extension of the existing basement level carpark previously permitted (providing 861 spaces in total). The total gross floor area for the proposed development is 13,883sq.m. Permission also for associated and ancillary development that will consist of a service yard, refuse areas, hard and soft landscaping, basement level plant and store rooms and all associated site development works. The main vehicular access point to the development is from the existing Western Distributor Road Roundabout Junction with access to the proposed service yard and underground car park located to the north of the main block off the internal proposed service yard and underground car park located to the north of the main block off the internal estate road.
Development Address:
Galway West District Centre, Western Distributor Road, Rahoon
Architect Name:
Location Key:
GALWAY WEST DISTRICT CENTRE
Electoral Division:
Planner:
John Doody
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Ext. of duration of planning permission to 04/01/2019 - M.O. 64287 (See also 08/567)
Decision
Decision Date:
29/01/2014
Manager Order:
64287
Decision Type:
Number of Conditions:
0
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
28/01/2015
Decision Description:
E.O.D. on Pl. Ref. 08/567. Permission for development on lands (1.425ha). The proposed development is Phase 2 of Galway West District Centre and involves the revision to the previously permitted Phase 2 proposals (Reg. Ref. 06/435, Ref.: Pl.61.222699) and extension of the site to the north that will result in the omission of the previously permitted 4 no. residential blocks (34 no. apartments), 1 no. office and a creche permitted under Reg. Ref.: 06/399. The proposed development comprises the following: - standalone 3-4 storey block located on the northern side of new pedestrian link to Bothar Stiofan comprising: creche at ground floor level (240sq.m) with external play area; management office (247sq.m) at first floor level; 7 no. retail units at ground and first floor levels (8,762sq.m); primary health care facility at second and third floor with associated ground floor lobby/reception area (3,600sq.m) 3 no. restaurant/cafe units at ground and first floor level (976sq.m) located on the northern elevation of Unit 6 (Dunnes Stores) fronting the new pedestrian link. 2 no. ESB substations (58.25sq.m), Car parking will be provided at surface and basement level for 149 no. additional spaces which will be an extension of the existing basement level carpark previously permitted (providing 861 spaces in total). The total gross floor area for the proposed development is 13,883sq.m. Permission also for associated and ancillary development that will consist of a service yard, refuse areas, hard and soft landscaping, basement level plant and store rooms and all associated site development works. The main vehicular access point to the development is from the existing Western Distributor Road Roundabout Junction with access to the proposed service yard and underground car park located to the north of the main block off the internal proposed service yard and underground car park located to the north of the main block off the internal estate road.
Galway West District Centre Western Distributor Road Rahoon
Permission for development on lands (1.425 ha). The proposed development is Phase 2 of Galway West District Centre and involves revisions to the previously permitted Phase 2 proposals (Reg. Ref. 06/435, Ref.: Pl. 61.222699) and extension of the site to the north that will result in the omission of the previously permitted 4 no. residential blocks (34 no. apartments), 1 no. office and a creche permitted under Reg. Ref: 06/399. The proposed development comprises the following:- standalone 3-4 storey block located on the northern side of new pedestrian link to Bothar Stiofan comprising: creche at ground floor level (240 sq.m) with external play area; management office (247 sq.m) at first floor level; 7 no. retail units at ground and first floor levels (8,762 sq.m); primary health care facility at second and third floor with associated ground floor lobby/reception area (3,600 sq.m) 3 no. restaurant / cafe units at ground and first floor level (976 sq.m) located on the northern elevation of Unit 6 (Dunnes Stores) fronting the new pedestrian link. 2 no. ESB substations (58.25sq.m), Car parking will be provided at surface and basement level for 149 no. additional spaces which will be an extension of the existing basement level car park previously permitted (providing 861 spaces in total). The total gross floor area for the proposed development is 13,883 sq.m. Permission also for associated and ancillary development that will consist of a service yard, refuse areas, hard and soft landscaping, basement level plant and store rooms and all associated site development works. The main vehicular access point to the development is from the existing Western Distributor Road Roundabout Junction with access to the proposed service yard and underground car park located to the north of the main block off the internal estate road
Unit 12 Gateway Retail Park (Knocknacarra District Centre) Western Distributor Road Galway
Planning permission is sought for the development which will consist of a 66.5 sq.m free standing covered caged area for holding WEEE recyclables, a 11 sq.m dock shelter/weather canopy to the loading door to the North Elevation and a 4.5 sq.m dock shelter to the loading door on the West Elevation, all within the rear service yard along with all necessary and associated site works
Unit 12 Gateway Retail Park Western Distributor Road Galway
Permission for development which consists of the provision of 2no. 2293mm high x 4034mm wide signs comprising of individually illuminated letter fixed to metal grids and mounted on the existing internal walls at first floor level behind the existing external glazing and all associated ancillary works
No Environment Impact Assesments Associated with this Application