Planning application details ref: 2461497 Donegal County Council

100%100% Complete (warning)

Planning Application: 2461497 (Donegal County Council )
File Number: 2461497
Application Type: PERMISSION Planning Status: DECISION MADE
Received Date: 23/09/2024 Decision Due Date: 17/11/2024
Validated Date: 23/09/2024 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 15/11/2024
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By: 27/10/2024

Applicant Details

Applicant name: FUTURENERGY IRELAND DEVELOPMENT DAC
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: (1) A 10-YEAR PERMISSION FOR THE DEVELOPMENT OF A LONG DURATION ENERGY STORAGE (LDES) COMPOUND WITH A TOTAL SURFACE AREA OF C.2.9HA CONTAINING 248NO. BATTERY ENERGY STORAGE UNITS IN THE FORM OF METAL SHIPPING CONTAINERS [APPROXIMATELY 12.2M (L) X 2.6M (W) AND 2.9M (H) EACH] AND ASSOCIATED ANCILLARY CONTROL AND VENTILATION EQUIPMENT; (2) INSTALLATION OF AN ONSITE TRANSFORMER COMPOUND (C.3,600SQ M) TO FACILITATE AN UNDER-THE FENCE CONNECTION TO THE ADJACENT TRILLICK 110KV SUBSTATION. THE TRANSFORMER COMPOUND WILL INCLUDE A CONTROL BUILDING OF C.27SQ M, A 110 KV TRANSFORMER, ASSOCIATED ELECTRICAL EQUIPMENT, AND AN UP TO 18M HIGH LIGHTNING PROTECTION MONOPOLE MAST; (3) A TEMPORARY CONSTRUCTION COMPOUND WITH A TOTAL SURFACE AREA OF C.1,500SQ M. C.515M OF NEW AND UPGRADED ACCESS TRACKS; 3NO. ENTRANCES FROM THE L-7231 PUBLIC ROAD COMPRISING THE UPGRADE OF 1NO. EXISTING ENTRANCE AND CREATION OF 1NO. NEW PERMANENT ACCESS AND 1NO. NEW TEMPORARY ACCESS FOR THE CONSTRUCTION AND OPERATION OF THE FACILITY; (4) UNDERGROUND ELECTRICAL AND COMMUNICATIONS CABLING BETWEEN THE PROPOSED LDES COMPOUND AND THE PROPOSED ON-SITE TRANSFORMER COMPOUND WHICH WILL CROSS UNDER THE L-7231 PUBLIC ROAD; (5) SECURITY LIGHTING; (6) POLE MOUNTED CCTV AND COMMUNICATIONS MAST; (7) ON-SITE FRESHWATER STORAGE TANK INCLUDING FRESH WATER TREATMENT UNIT IN THE FORM OF A METAL SHIPPING CONTAINER; (8) ON-SITE DRAINAGE SYSTEM AND ASSOCIATED VEGETATED ATTENUATION POND; (9) A STORAGE CONTAINER IN THE FORM OF A METAL SHIPPING CONTAINER; (10) SOUND REFLECTIVE BARRIERS TO A HEIGHT OF 4M; (11) SECURITY FENCING AND GATES; AND ALL ASSOCIATED ANCILLARY SITE DEVELOPMENT, SERVICES AND CLEARANCE WORKS INCLUDING TREE FELLING OF C.4.7HA OF CONIFER PLANTATION; LANDSCAPING AND PLANTING. THE PROPOSED LDES FACILITY WILL BE OPERATIONAL FOR A PERIOD OF 30 YEARS
Development Address: BALLYNAHONE, BUNCRANA, LIFFORD PO, CO. DONEGAL
Architect Name: Location Key: BALLYNAHONE
Electoral Division: Fahan Planner: RYAN NOLAN
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 15/11/2024 Manager Order: 2024PH2844
Decision Type: Conditional Number of Conditions: 37
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date:
Decision Description: (1) A 10-YEAR PERMISSION FOR THE DEVELOPMENT OF A LONG DURATION ENERGY STORAGE (LDES) COMPOUND WITH A TOTAL SURFACE AREA OF C.2.9HA CONTAINING 248NO. BATTERY ENERGY STORAGE UNITS IN THE FORM OF METAL SHIPPING CONTAINERS [APPROXIMATELY 12.2M (L) X 2.6M (W) AND 2.9M (H) EACH] AND ASSOCIATED ANCILLARY CONTROL AND VENTILATION EQUIPMENT; (2) INSTALLATION OF AN ONSITE TRANSFORMER COMPOUND (C.3,600SQ M) TO FACILITATE AN UNDER-THE FENCE CONNECTION TO THE ADJACENT TRILLICK 110KV SUBSTATION. THE TRANSFORMER COMPOUND WILL INCLUDE A CONTROL BUILDING OF C.27SQ M, A 110 KV TRANSFORMER, ASSOCIATED ELECTRICAL EQUIPMENT, AND AN UP TO 18M HIGH LIGHTNING PROTECTION MONOPOLE MAST; (3) A TEMPORARY CONSTRUCTION COMPOUND WITH A TOTAL SURFACE AREA OF C.1,500SQ M. C.515M OF NEW AND UPGRADED ACCESS TRACKS; 3NO. ENTRANCES FROM THE L-7231 PUBLIC ROAD COMPRISING THE UPGRADE OF 1NO. EXISTING ENTRANCE AND CREATION OF 1NO. NEW PERMANENT ACCESS AND 1NO. NEW TEMPORARY ACCESS FOR THE CONSTRUCTION AND OPERATION OF THE FACILITY; (4) UNDERGROUND ELECTRICAL AND COMMUNICATIONS CABLING BETWEEN THE PROPOSED LDES COMPOUND AND THE PROPOSED ON-SITE TRANSFORMER COMPOUND WHICH WILL CROSS UNDER THE L-7231 PUBLIC ROAD; (5) SECURITY LIGHTING; (6) POLE MOUNTED CCTV AND COMMUNICATIONS MAST; (7) ON-SITE FRESHWATER STORAGE TANK INCLUDING FRESH WATER TREATMENT UNIT IN THE FORM OF A METAL SHIPPING CONTAINER; (8) ON-SITE DRAINAGE SYSTEM AND ASSOCIATED VEGETATED ATTENUATION POND; (9) A STORAGE CONTAINER IN THE FORM OF A METAL SHIPPING CONTAINER; (10) SOUND REFLECTIVE BARRIERS TO A HEIGHT OF 4M; (11) SECURITY FENCING AND GATES; AND ALL ASSOCIATED ANCILLARY SITE DEVELOPMENT, SERVICES AND CLEARANCE WORKS INCLUDING TREE FELLING OF C.4.7HA OF CONIFER PLANTATION; LANDSCAPING AND PLANTING. THE PROPOSED LDES FACILITY WILL BE OPERATIONAL FOR A PERIOD OF 30 YEARS

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: