Planning Application: 16363 (Wicklow County Council )
File Number:
16363
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
08/04/2016
Decision Due Date:
30/11/2016
Validated Date:
08/04/2016
Invalidated Date:
Further Info Requested:
01/06/2016
Further Info Received:
03/11/2016
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
24/11/2016
Leave to Appeal:
Appeal Date:
19/12/2016
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Irish Water
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
water treatment plant including a water treatment building (gross area of approx 4670 sqm) a low lift pumping station, sludge treatment facilities including a sludge dewatering building, sludge balancing tank, thickening tanks, sludge holding tank and sludge storage tank and sludge storage facility, washwater recovery and settlement tanks and an electrical distribution building to replace the existing water treatment scheme, alteration to the existing reservoir offtake tower, addition and alteration to pipework and structures within the existing reservoir dam, construction of a piped siphon over the existing reservoir dam, demolition of a disused public toilet, regrading of the existing overflow spillway and associated landscaping and site development works
Development Address:
Vartry Water Treatment Site, Vartry, Roundwood, Co Wicklow
water treatment plant including a water treatment building (gross area of approx 4670 sqm) a low lift pumping station, sludge treatment facilities including a sludge dewatering building, sludge balancing tank, thickening tanks, sludge holding tank and sludge storage tank and sludge storage facility, washwater recovery and settlement tanks and an electrical distribution building to replace the existing water treatment scheme, alteration to the existing reservoir offtake tower, addition and alteration to pipework and structures within the existing reservoir dam, construction of a piped siphon over the existing reservoir dam, demolition of a disused public toilet, regrading of the existing overflow spillway and associated landscaping and site development works