Planning Application: 2250933 (Donegal County Council )
File Number:
2250933
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
30/05/2022
Decision Due Date:
14/01/2023
Validated Date:
30/05/2022
Invalidated Date:
Further Info Requested:
22/07/2022
Further Info Received:
23/11/2022
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
13/01/2023
Leave to Appeal:
Appeal Date:
07/02/2023
Commenced Date:
Submissions By:
22/12/2022
Applicant Details
Applicant name:
PATRICK BONAR
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
(1) DEMOLITION OF EXISTING CONCRETE STRUCTURE (2) QUARRYING OF 5.37 HECTARES WHICH WILL BE SUBJECT TO EXTRACTION AND PROCESSING OF ROCK THROUGH DRILLING, BLASTING, CRUSHING AND SCREENING (3) CONSTRUCTION OF (A) SETTLEMENT PONDS AND WETLAND (B) A SHED FOR THE PURPOSES OF STORAGE FOR THE FACILITY INCLUDING ON-SITE MACHINERY MAINTENANCE (C) SITE OFFICE WITH CANTEEN, TOILET & DRYING FACILITIES (4) INSTALLATION OF A WASTEWATER TREATMENT SYSTEM & PERCOLATION AREA (5) PROVISION OF A WHEEL WASH AND WEIGHBRIDGE (6) LANDSCAPING OF THE QUARRY DURING THE OPERATIONAL PHASE AND RESTORATION OF THE QUARRY ON COMPLETION OF EXTRACTION (7) ALL ASSOCIATED ANCILLARY FACILITIES / WORKS OVER A 25 YEAR PERIOD. AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) & NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
(1) DEMOLITION OF EXISTING CONCRETE STRUCTURE (2) QUARRYING OF 5.37 HECTARES WHICH WILL BE SUBJECT TO EXTRACTION AND PROCESSING OF ROCK THROUGH DRILLING, BLASTING, CRUSHING AND SCREENING (3) CONSTRUCTION OF (A) SETTLEMENT PONDS AND WETLAND (B) A SHED FOR THE PURPOSES OF STORAGE FOR THE FACILITY INCLUDING ON-SITE MACHINERY MAINTENANCE (C) SITE OFFICE WITH CANTEEN, TOILET & DRYING FACILITIES (4) INSTALLATION OF A WASTEWATER TREATMENT SYSTEM & PERCOLATION AREA (5) PROVISION OF A WHEEL WASH AND WEIGHBRIDGE (5) LANDSCAPING OF THE QUARRY DURING THE OPERATIONAL PHASE AND RESTORATION OF THE QUARRY ON COMPLETION OF EXTRACTION (5) ALL ASSOCIATED ANCILLARY FACILITIES / WORKS OVER A 25 YEAR PERIOD. AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) & NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
(1) QUARRYING OF 4.81 HECTARES WHICH WILL BE SUBJECT TO EXTRACTION AND PROCESSING OF ROCK BY DRILLING, BLASTING, CRUSHING AND SCREENING (2) LANDSCAPING OF THE QUARRY DURING THE OPERATIONAL PHASE AND RESTORATION OF THE QUARRY ON COMPLETION OF EXTRACTION (3) ERECTION OF SITE OFFICE WITH CANTEEN FACILITIES (4) INSTALLATION OF WASTEWATER TREATMENT UNIT & PERCOLATION AREA (5) ALL ASSOCIATED ANCILLARY FACILITIES / WORKS OVER A 25 YEAR PERIOD
(1) QUARRYING OF 5.37 HECTARES WHICH WILL BE SUBJECT TO EXTRACTION AND PROCESSING OF ROCK THROUGH DRILLING, BLASTING, CRUSHING AND SCREENING (2) CONSTRUCTION OF (A) SETTLEMENT PONDS AND CONSTRUCTED WETLAND (B) A SHED FOR THE PURPOSES OF STORAGE FOR THE FACILITY INCLUDING THE ON-SITE MACHINERY MAINTENANCE (C) SITE OFFICE WITH CANTEEN, TOILET & DRYING FACILITIES (3) INSTALLATION OF A WASTEWATER TREATMENT SYSTEM & PERCOLATION AREA (4) PROVISION OF A WHEEL WASH AND WEIGHBRIDGE (5) LANDSCAPING OF THE QUARRY DURING THE OPERATIONAL PHASE AND RESTORATION OF THE QUARRY ON COMPLETION OF EXTRACTION (5) ALL ASSOCIATED ANCILLARY FACILITIES / WORKS OVER A 25 YEAR PERIOD. AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) & NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION