Planning application details ref: 2360264 Cavan CoCo

100%100% Complete (warning)

Planning Application: 2360264 (Cavan CoCo)
File Number: 2360264
Application Type: PERMISSION Planning Status: APPEALED
Received Date: 08/11/2023 Decision Due Date: 10/04/2024
Validated Date: 08/11/2023 Invalidated Date:
Further Info Requested: 11/01/2024 Further Info Received: 28/02/2024
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 05/04/2024
Leave to Appeal: Appeal Date: 02/05/2024
Commenced Date: Submissions By: 27/03/2024

Applicant Details

Applicant name: Accelerate Renewables Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: for: A ten-year planning permission for an energy storage facility comprising (i) energy storage containers installed on concrete plinths; (ii) power conversion systems; (iii) power control centre units; (iv) underground electrical and communications cabling; (v) the upgrade of an existing agricultural access point from the L2512; (vi) on-site access track; (vii) security fencing and security gates; (viii) pole-mounted security cameras; and (ix) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. This planning application is accompanied by an Appropriate Assessment Screening Report
Development Address: Pottle, Ballinagh, Co. Cavan
Architect Name: Location Key: Pottle, Ballinagh
Electoral Division: Planner:
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 05/04/2024 Manager Order: PL 104,996
Decision Type: Conditional Number of Conditions: 26
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date:
Decision Description: for: A ten-year planning permission for an energy storage facility comprising (i) energy storage containers installed on concrete plinths; (ii) power conversion systems; (iii) power control centre units; (iv) underground electrical and communications cabling; (v) the upgrade of an existing agricultural access point from the L2512; (vi) on-site access track; (vii) security fencing and security gates; (viii) pole-mounted security cameras; and (ix) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. This planning application is accompanied by an Appropriate Assessment Screening Report

Appeal Details


Appeal Details
Notification Date: 07/05/2024 BP Reference #: ABP-319637-24
Appeal Type: THIRD PARTY File Forward Date:
Submission Due Date: 03/06/2024 Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: